Works are continuing on multiple fronts for our client Balfour Beatty VINCI on HS2


14-Sep-2023

Works are continuing on multiple fronts for our client Balfour Beatty VINCI on HS2 (High Speed Two) Ltd. Here are some photographs of our teams’ efforts taken over the last number of weeks.
 
We have been busy installing sheet piles and propping systems, completing excavations and pile breakdown, as well as all of the temporary works designs associated with the package of complex temporary works.
 
Sheet piles have generally been installed into mudstones with our powerful multi-function ABI TM22 rigs, with some conventional sheet piling where access was restricted. Propping provided was tailored to meet the requirements of each individual solution, with a mixture of proprietary systems as well as our own inhouse modular propping solution.