Please enable JS

Somerset: AAVUEST at RNAS Yeovilton

 

PROJECT DETAILS

CLIENT:
Royal Navy

DESIGN ENGINEER:
AECOM

MAIN CONTRACTOR:
Galliford Try

DAWSON-WAM was contracted by Galliford Try to construct new secant walls and load bearing piles to facilitate the construction of the new Aircraft/Amphibious Vehicle Underwater Escape and Survival Training (AAVUEST) at RNAS Yeovilton in Somerset. The new centre will contain pools to train personnel in escaping from a submerged aircraft or amphibious vehicle

The deal was let through the DIO’s Next Generation Estates Contracts (NGEC) National Capital Works Framework. Construction of the dunk tanks forms part of the MOD’s commitment to modernise the military infrastructure and ensure the best possible safety training for the UK’s Armed Forces.

Simon Jones, Project Manager at the DIO said: “Building this facility is an important part of our commitment to world-class military training and the signing of this contract is an important first milestone in this process.

The existing site was a greenfield space adjacent to the base and the piling footprint was approximately 80m by 50m. Ground conditions were gravels overlaying stiff clay which became mudstone at a shallow depth. The water table was just below existing ground level which encouraged the use of a secant piled solution for excavations.

The new development required the creation of two individual excavations to depths of 5.5m below ground level. Due to the construction sequence propping was limited to capping beam level with props positioned at uneven centres meaning that considerable unbalanced forces had to be considered.

In all 200lm of 630mm, diameter secant walls were installed with piles ranging in length up to 11m. Hard/Hard secant walls were installed using DAWSON-WAM’s Cased CFA System mounted on an ABI TM22 piling rig and were installed up to 6m into the underlying mudstone rock and to very strict vertical tolerances of over 1:150.

DAWSON-WAM also installed 96nr Cased CFA load bearing piles of 630mm and 450mm diameter and to depth of 13m. Reinforcement was pushed down to cut off level to assist the following trades in breaking down the piles. All piles were integrity tested and 1 static load test was completed and performed extremely well.