Multi-discipline Foundation Package Completed for Gilbert-Ash in Farringdon


16-Sep-2021

DAWSON-WAM have recently completed all of the works on site in Farringdon for Gilbert-Ash, and it was great to return to see the excavation progression.

We completed the multi discipline foundation package over four phases which included testing of existing bearing piles, installation of new 900mm diameter piles to 30m, installation of sheet pile retaining walls and finally installation of temporary propping.

All the works were completed in a busy city centre environment with works taking place over and immediately adjacent to live Network Rail Tunnels.