M6 J13-15 Smart Motorway Project Update


5-Jun-2020

Over the past 5 months we have completed phases 3, 4 and 5 on the M6 J13-15 Smart Motorway for Kier Group and are looking forward to return to install the 6th and final phase from July 2020. This last 5 months has seen us install over 2,000 linear metres of sheet piles in over 50 separate walls working adjacent to sensitive services such as medium pressure gas mains and cast-iron water trunk mains. Sheet piles were installed up to 12m into sandstone and 14m into mudstone with the UKs most powerful sheet piling equipment without the need for any impact driving.