Contiguous Wall Complete for Coventry Accommodation Complex


6-Jul-2020

Over the past few months we have completed all the contiguous wall and load bearing piles on a 17 storey accommodation block in Coventry for Farrans Construction.

Piles were installed up to 19.5m in length, through layers of Stiff Clay, Sandstone and Mudstone, by our powerful RTG RG25S using Cased CFA techniques with rock sockets of up to 8m in length.

The site was situated on an existing contoured car park, with a difference of ground levels across the site of over 7m, mean 6 different piling platform levels, and a requirement for the rig to pile above itself to form the contig wall.